A Perfect Breakthrough for the First Jacking Section of Ulaanbaatar Water Diversion Project Section in Mongolia

  • 2025-04-02

Date: February 2025

Location: Ulaanbaatar, Mongolia

Project name: Ulaanbaatar Water Diversion Project

Project type: Water Diversion Project

Equipment details:Tangxing Technology HRC1200 rock pipe jacking machine

Jacking distance: 240 meters of the first jacking section was successfully completed

Difficulties: sand and pebble geology, rich groundwater, crossing the river

Project significance: It can help Ulaanbaatar to crack the bottleneck of water shortage and ensure the sustainable development and ecological safety of the city.





CONTACT US

EUROPE
Tangxing_Edward
+6010-397 6995
T1SERVICE@TANGXING.CN
MIDDLE EAST OR ASIA
Tangxing_Michael
+6010-293 6995
T2SERVICE@TANGXING.CN
AFRICA
Tangxing_Bonnie
+6010-825 6995
T3SERVICE@TANGXING.CN
AMERICAS
Tangxing_lvy
+8615305547358
IVY@TANGXING.CN

Sales hotline:86-0554-2796608

Copyright: Tangxing Machinery Record:皖ICP备16015277号-3